Bond Program » Measure CC Bond Updates » February 2026

February 2026

Construction Beat Measure CC Bond Update

Bond Messaging - February 2026

LGUSD

What’s happening now:  We held our first Citizen’s Bond Oversight Committee meeting on February 2, 2026. This volunteer group ensures that voter-approved bond funds are spent properly on our schools and students. We still have a few openings on the committee. If you would like to help oversee these important projects, please visit the Citizen’s Bond Oversight Committee webpage where you will find information and the application.  


Questions?  Contact Teresa Fiscus, Chief Business Official, at [email protected].

RJ Fisher Middle School

MPR, Music, & Kitchen

  • What’s happening now: We have completed the schematic design phase. The project team will now focus  on refining design details, finalizing specifications, and preparing construction documents. 

  • Timeline: Progress remains on schedule with construction beginning June 2027.

HVAC Update

  • What’s happening now:  The State asked for more details on our plans. Our team has submitted that information and we are now waiting for their final approval.

  • Timeline:  Because of the extra step in the approval process, we are tentatively targeting mid Summer to begin construction.

Security Cameras

  • What’s happening now: LGUSD leaders and school staff have met to identify the best spots for new cameras. We are now working with a security expert to finalize the specific types of technology and systems that will be best for our schools.

  • Timeline:  The Bond Management Team is currently determining if this work can be completed this Summer. 

Traffic Study

  • What’s happening now: We have finished the first round of our traffic study with the traffic consultants and are reviewing the initial traffic report.    

  • Timeline:  A follow-up visit to RJ Fisher is targeted for early March to perform a traffic study at different times and days of the week to gather additional information regarding site concerns.

Van Meter

HVAC Update

  • What’s happening now:  The State has officially accepted our project plans and is now performing a detailed safety and design review. Meanwhile, our team is double-checking the blueprints to ensure they are ready for building. We are also preparing to invite contractors to bid on the project, with a meeting scheduled for March 12, 2026.

  • Timeline:  We hope to start construction this summer. Our schedule depends on how quickly we receive final approval of our plans. 

Security Cameras

  • What’s happening now: LGUSD leaders and school staff have met to identify the best spots for new cameras. We are now working with a security expert to finalize the specific types of technology and systems that will be best for our schools.

  • Timeline:  The Bond Management Team is currently determining if this work can be completed this Summer. 

Traffic Study

  • What’s happening now: We have finished the first round of our traffic study with the traffic consultants and are reviewing the initial traffic report.    

  • Timeline:  A follow-up visit to Van Meter is targeted for early March to perform a traffic study at different times and days of the week to gather additional information regarding site concerns. 

Lexington

HVAC Controls Project Update

  • What’s happening now:  We have officially launched the project after meeting with our installation team on-site to finalize the plan. All necessary equipment and materials have been delivered and are ready for use.

  • Timeline:  The first phase of installation began over the February Recess.  We expect the entire project to be completed during Spring Break in April.  

Security Cameras

  • What’s happening now: LGUSD leaders and school staff have met to identify the best spots for new cameras. We are now working with a security expert to finalize the specific types of technology and systems that will be best for our schools.

  • Timeline:  The Bond Management Team is currently determining if this work can be completed this Summer. 

Blossom Hill

Security Cameras

  • What’s happening now: LGUSD leaders and school staff have met to identify the best spots for new cameras. We are now working with a security expert to finalize the specific types of technology and systems that will be best for our schools.

  • Timeline:  The Bond Management Team is currently determining if this work can be completed this Summer. 

Daves Avenue

Security Cameras

  • What’s happening now: LGUSD leaders and school staff have met to identify the best spots for new cameras. We are now working with a security expert to finalize the specific types of technology and systems that will be best for our schools.